Written 06/04/05
The County Council's contractors have made the following information available about their current plans for the road closures necessary to do the surfacing works to complete the traffic calming scheme.
April
Monday 11th to Tuesday 12th - Milton Road (from IVC to A10)
Thursday 14th to Wednesday 20th - Impington Lane (from B1049 to IVC)
Monday 25th to Thursday 28th - New Road (from IVC to B1049)
May
Tuesday 3rd to Friday 6th - Park Lane (from Oakington Road to Bell Hill)
Monday 9th to Thursday 12th - Station Road (from High Street to Saffron Road)
Tuesday 17th to Wednesday 18th - Cambridge Road (from Cambridge Road to Chequers Road)
Note: Access to Chivers Way will be maintained throughout the surfacing of its junction table by the use of Stop and Go boards.
Closures will all be off peak between the hours 09.15 to 16.15 Monday to Friday and will only be used where necessary. Diversionary signing will be
set up around the area for each closure. Access will be maintained for residents and businesses.
|